Roadway Improvements Project Number: 1072 Council District(s): 06

15th St Extension

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the extension of 15th St two blocks westward from West Peachtree St to Williams St to improve traffic circulation for vehicles, bicycles, and pedestrians through the Midtown area.

Percent Complete

13%

Paid

$188,625

Target Project Start

Nov. 2016

Target Design Finish

Oct. 2022

Target Construction Start

Jun. 2023

Target Construction Finish

Jun. 2025

Disclaimer: Project budgets, schedules and scopes are subject to change.