ADA Improvements - FC-8250

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes ADA improvements at West Paces Ferry, Tye St, North Ave, Sylvan Rd, Sheridan Rd, Moores Mill Rd, Linden Ave, Lindbergh Way, Flat Shoals Rd, North Camp Creek Pkwy, Cheshire Bridge Rd, McLendon Ave, Oakdale Rd, Loridans Dr, Mayson St, Empire Industrial Blvd, College Ave, Fair St, Lawton St, Ruby Harper Blvd, Southside Industrial Ct, Southside Industrial Pkwy, Southside Industrial Way, Wilson Rd, Decatur St, and Guilford Forest Dr.

Percent Complete

45%

Paid

$1,334,949

Target Project Start

Aug. 2016

Target Design Finish

Jul. 2018

Target Construction Start

Mar. 2017

Target Construction Finish

Nov. 2018

Disclaimer: Project budgets, schedules and scopes are subject to change.