Sidewalks & Mobility Project Number: 1090 Council District(s): 08

Atlanta Memorial Park Pedestrian Access and Safety Improvements

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the construction of a new bicycle and pedestrian bridge between Dellwood Dr and Colonial Homes Cir over Peachtree Creek along with 0.91 miles of concrete sidewalk along Woodward Way NW (Bobby Jones).

Percent Complete

100%

Paid

$1,875,335

Target Project Start

Sep. 2016

Target Design Finish

Aug. 2017

Target Construction Start

Dec. 2017

Target Construction Finish

Nov. 2018