Traffic Signals Project Number: 1049 Council District(s): 04, 11, 12

Campbellton Rd Signals

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the replacement of traffic signal LEDs, cabinets, controller monitors, signal wirings, communications, ADA ramps and timing at multiple intersections between Lee St and Greenbriar Pkwy.

Percent Complete

87%

Paid

$928,818

Target Project Start

Oct. 2015

Target Design Finish

Mar. 2018

Target Construction Start

Feb. 2016

Target Construction Finish

May. 2020

Disclaimer: Project budgets, schedules and scopes are subject to change.