Traffic Signals Project Number: 1050 Council District(s): 02, 03, 04

Centennial Olympic Park Dr (TCC)

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes signal upgrades, fiber communications, and signal timing optimization from Marietta St to North Ave.

Percent Complete

78%

Paid

$653,944

Target Project Start

Aug. 2016

Target Design Finish

Feb. 2018

Target Construction Start

May. 2017

Target Construction Finish

Jul. 2019

Disclaimer: Project budgets, schedules and scopes are subject to change.