Bridges Project Number: 1020 Council District(s): 01, 04

Central Ave Bridge

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes bridge replacement from Martin Luther King (MLK) Jr Dr to Decatur St. Work includes new lighting, repair of approaches, and modification of curbing to create a full lane between Wall St and Decatur St. Parking to be determined through coordination with the Department of Public Works - Office of Transportation.

Percent Complete

19%

Paid

$1,457,831

Target Project Start

Oct. 2016

Target Design Finish

Oct. 2021

Target Construction Start

Apr. 2022

Target Construction Finish

Feb. 2024

Disclaimer: Project budgets, schedules and scopes are subject to change.