Traffic Signals Project Number: 1071 Council District(s): 01, 02, 03, 04, 05, 06, 07, 08

Citywide ITS/Signal

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the replacement of traffic signal cabinets, minor signal upgrades, controllers, signal wiring, ADA ramps, fiber installation, and signal timing at multiple intersections. Locations include: 14th St, Courtland Ave, Juniper St, Linden Ave, Monroe Dr at Park Dr, Monroe Dr, Pine St, Ponce De Leon Ave, Spring St, Ted Turner Dr signal, W Peachtree St, Juniper St, Roxboro Rd, Monroe Dr, 10th St, Northside Dr at Marietta St, and Piedmont Ave. Mount Paran Rd at Northside Pkwy scope also includes intersection improvements.

Percent Complete

9%

Paid

$534,155

Target Project Start

Mar. 2016

Target Design Finish

Aug. 2018

Target Construction Start

Dec. 2020

Target Construction Finish

Oct. 2022

Disclaimer: Project budgets, schedules and scopes are subject to change.