Roadway Improvements Project Number: 1073 Council District(s): 01, 02, 05

DeKalb Ave Safety Improvements

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes upgrading traffic signal coordination and intersection improvements, resurfacing of Dekalb Ave from Jackson Street to Ridgecrest Road, and removal of the reversible lane from Jackson Street to Oxford Place. Protected bike lanes have been proposed as part of the Mayor's Action Plan for Safer Streets Across Atlanta.

Percent Complete

16%

Paid

$908,850

Target Project Start

Feb. 2016

Target Design Finish

Jun. 2020

Target Construction Start

Nov. 2020

Target Construction Finish

Nov. 2021

Disclaimer: Project budgets, schedules and scopes are subject to change.