Complete Street Project Number: 1008 Council District(s): 03

J E Boone Boulevard Complete Street

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes resurfacing, sidewalks, and green infrastructure along JE Boone Blvd from Northside Dr to Mayson Turner Rd.

Percent Complete

33%

Paid

$656,967

Target Project Start

Apr. 2016

Target Design Finish

Apr. 2017

Target Construction Start

Nov. 2016

Target Construction Finish

Dec. 2020

Disclaimer: Project budgets, schedules and scopes are subject to change.