Complete Street Project Number: 1010 Council District(s): 10, 11

Lynhurst Drive Complete Street

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes resurfacing and restriping, ADA-compliant ramps, sidewalks, and pedestrian lighting along Lynhurst Dr from Cascade Rd to Martin Luther King (MLK) Jr Dr.

Percent Complete

100%

Paid

$2,990,682

Target Project Start

Jul. 2015

Target Design Finish

Nov. 2015

Target Construction Start

Jul. 2015

Target Construction Finish

Jan. 2018

Disclaimer: Project budgets, schedules and scopes are subject to change.