Traffic Signals Project Number: 1054 Council District(s): 02, 03, 06

Midtown CID Improvements

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Four (4) intersection improvements on Peachtree St at 14th St, 15th St, Peachtree Cir, and Buford-Spring Connector. Includes new curb, ADA upgrades, sidewalk replacement, crosswalk restriping, vehicle detection at signals, and mast arm traffic signals.

Percent Complete

100%

Paid

$458,913

Target Project Start

Sep. 2017

Target Design Finish

Oct. 2017

Target Construction Start

Aug. 2018

Target Construction Finish

Aug. 2019

Disclaimer: Project budgets, schedules and scopes are subject to change.