Complete Street Project Number: 1011 Council District(s): 03, 04, 10

MLK Jr. Dr Complete Street

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes resurfacing, restriping, bicycle lanes, landscaping, and traffic improvements from Northside Dr to Fulton Industrial Blvd. Work also includes a protected bike and pedestrian facility from Sunset Ave to Northside Dr.

Percent Complete

60%

Paid

$10,200,326

Target Project Start

May. 2017

Target Design Finish

Nov. 2017

Target Construction Start

Jun. 2018

Target Construction Finish

Mar. 2021

Disclaimer: Project budgets, schedules and scopes are subject to change.