Complete Street Project Number: 1013 Council District(s): 06

Monroe Dr Complete Street

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes resurfacing and pedestrian improvements between Piedmont Circle and 10th St. Signal improvements at intersections to include replacement of traffic signal LEDs, cabinets, controller monitors, signal wiring, communications, and signal timing.

Percent Complete

3%

Paid

$192,563

Target Project Start

May. 2016

Target Design Finish

Jul. 2022

Target Construction Start

Jan. 2023

Target Construction Finish

Jan. 2024

Disclaimer: Project budgets, schedules and scopes are subject to change.

Previous Meetings