Roadway Improvements Project Number: 1080 Council District(s): 07

Piedmont Rd Capacity Improvement

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the widening of Piedmont Road/SR 237 between Peachtree Rd and Lenox Rd from 5 lanes (two travel lanes in each direction and a center two-way left-turn lane) to 7 lanes (three travel lanes in each direction and a center two-way, left-turn lane). Also includes landscaping, signage, signalization, and a 12-foot multi-use path on the west side of Piedmont Rd.

Percent Complete

10%

Paid

$402,839

Target Project Start

Jan. 2018

Target Design Finish

Feb. 2021

Target Construction Start

Jun. 2021

Target Construction Finish

Nov. 2021