Bridges Project Number: 1025 Council District(s): 08

Powers Ferry Rd Bridge

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Bridge replacement over Nancy Creek from Pineland Rd to Hillside Dr. Work includes installation of two 12-foot lanes and a 10-foot-wide, multi-use trail on the east side of Powers Ferry Rd.

Percent Complete

100%

Paid

$2,904,230

Target Project Start

Oct. 2015

Target Design Finish

Jun. 2017

Target Construction Start

Jul. 2018

Target Construction Finish

Sep. 2019

Disclaimer: Project budgets, schedules and scopes are subject to change.