Sidewalks & Mobility Project Number: 1105 Council District(s): 08

Putnam Drive Sidewalks

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes the construction of sidewalks along Putman Drive between Blackland Road and Powers Ferry Road.

Percent Complete

0%

Paid

$0

Target Project Start

Jul. 2020

Target Design Finish

Mar. 2021

Target Construction Start

Sep. 2021

Target Construction Finish

Feb. 2022