Complete Street Project Number: 1096 Council District(s): 01

South Boulevard Complete Streets

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

CONCEPT STUDY ONLY. Concept study to evaluate improvement alternatives to provide protected bike and pedestrian facilities along South Boulevard from Woodward Ave to McDonough Blvd.

Percent Complete

1%

Paid

$21,198

Target Project Start

Sep. 2019

Target Design Finish

Dec. 2021

Target Construction Start

Jun. 2022

Target Construction Finish

Jun. 2023

Disclaimer: Project budgets, schedules and scopes are subject to change.