Resurfacing Project Number: 1035 Council District(s): 02, 04, 05

Streetcar Resurfacing (FC-9561)

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes resurfacing of Andrew Young International Blvd, Auburn Ave, Carnegie Way, Centennial Olympic Park Dr, Edgewood Ave, Ellis St, Fort St, Jackson St, Luckie St, Park Pl, and Peachtree St in partnership with Atlanta Streetcar.

Percent Complete

100%

Paid

$3,388,238

Target Project Start

Jul. 2016

Target Design Finish

Nov. 2016

Target Construction Start

Jun. 2017

Target Construction Finish

Jan. 2018

Disclaimer: Project budgets, schedules and scopes are subject to change.