Traffic Signals Project Number: 1068 Council District(s): 01, 11, 12

Traffic Combo 1

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes signal upgrades, pedestrian signal upgrades, ADA ramps, striping, intersection upgrades, detection, and signal timing coordination at the following: Claire Dr at 3 locations; Lakewood Ave at 3 locations; Sylvan Rd at 2 locations; and Cleveland Ave at 9 locations. Project also includes DESIGN ONLY of signal improvements on Sylvan Rd at 2 locations and Greenbriar Pkwy at 5 locations.

Percent Complete

9%

Paid

$296,118