Traffic Signals Project Number: 1069 Council District(s): 01, 04, 05, 12

Traffic Combo 2 (Design Only)

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

DESIGN ONLY. For fiber installation, minor signal upgrades, and signal removals on several corridors, including signal cabinet upgrades, vehicle detection, ADA ramps, and pedestrian push-button upgrades. Corridors include R D Abernathy Blvd/Georgia Ave, Atlanta Ave, Hosea Williams Dr, Boulevard, McDaniels St, and Glenwood Ave. Atlanta Ave includes signage to support one-way to two-way conversion.

Percent Complete

62%

Paid

$475,169

Target Project Start

Apr. 2016

Target Design Finish

Dec. 2020

Disclaimer: Project budgets, schedules and scopes are subject to change.