Traffic Signals Project Number: 1070 Council District(s): 01, 02, 03, 04, 05, 06, 08, 09, 10, 12

Traffic Combo 4

Phase

Not Started
Planning & Development
Design
Construction
Complete

Scope

Includes signal upgrades, pedestrian signal upgrades, ADA ramps, striping, intersection upgrades, and vehicle detection at 15 isolated locations throughout the city.

Percent Complete

13%

Paid

$362,999

Disclaimer: Project budgets, schedules and scopes are subject to change.